| Date | Business performance | Remark |
|---|---|---|
| 2009. 03. 24 ~ 05. 20 | Manufactured and delivered BFP rotor for Samcheonpo Thermal Power Plant. | |
| 2009. 02. 17 ~ 03. 19 | Overhauled COP, CWP, CCWP, and CVP of 2 BFPs at Hadong Thermal Power Plant. | |
| 2009. 02. 15 ~ 03. 13 | Overhauled CEP at GE Energy and supplied parts. | |
| 2009. 01. 05 ~ 02. 20 | Repaired and assembled fl owserve BFP. | |
| 2009. 01. 05 ~ 01. 15 | Repaired and commissioned CWP impeller and suction cone at Samcheongpo Thermal Power Plant. | (Domestic products) |
| 2008. 11. 01 ~ 12. 31 | Manufactured and commissioned 10-stage LPDP for Youngheung Thermal Power Plant. | |
| 2008. 11. 01 ~ 11. 30 | Overhauled and commissioned 6 BFP at Hadong Thermal Power Plant No. 7 and No. 8. | (Domestic products) |
| 2008. 05. 01 ~ 11. 30 | Replaced and overhauled BFP parts for Shinincheon Thermal Power Plant. (6 units) | (Imported products) |
| 2008. 03. 30 ~ 04. 20 | Disassembled and overhauled COP at Gyeongju World. | |
| 2008. 03. 15 ~ 04. 10 | Repaired rotor of circulation water pump at Samcheonpo Thermal Power Plant. | |
| 2008. 02. 20 ~ 03. 30 | Replaced and overhauled BFP parts at Daegu Combined Cycle Plant. | (Japan) |
| 2008. 02. 20 ~ 03. 27 | Overhauled and commissioned 3 BFPs and 3 BFBPs for Hadong Thermal Power Plant No. 7. | (Domestic products) |
| 2007. 10. 05 ~ 12. 31 | Overhauled BFP at Shinincheon Thermal Plant, Hadong Thermal Plant, and Samcheonpo Thermal Plant for effi ciency improvement. | (Germany and USA) |
| 2007. 09. 20 ~ 10. 10 | Assembled API pumps for SK (Sahara) 350 R2. | KS 350R2 Model |
| 2007. 08. 20 ~ 08. 09 | Assembled API pumps for SK-L Project. | UCW Model |