Date | Business performance | Remark |
---|---|---|
2007. 06. 30 ~ 08. 20 | Assembled API pumps for New FCC project. | 150*100R2 Model |
2007. 06. 30 ~ 07. 20 | Assembled BFP for Hanwha Chemical Corp. | 150 SPD Model |
2007. 06. 25 ~ 06. 26 | Overhauled BFP at OCI Company Ltd. | MSS Model |
2007. 06. 20 ~ 06. 25 | Manufactured hydraulic turbines for Hyosung Research Center. | 5KW - 50KW |
2007. 06. 10 ~ 06. 20 | Assembled BFPs for SKC and GS Caltex. | 150 SPD 8M,4M |
2007. 05. 10 ~ 05. 20 | Overhauled COP at Samcheonpo Thermal Power Plant. | (Domestic products) |
2007. 04. 30 ~ 05. 09 | Overhauled 10 IFWs at Samsung Total. | (Domestic products) |
2007. 03. 12 ~ 05. 20 | Localized CWP parts at Ulsan Thermal Power Plant. | (KSB of Germany) |
2007. 03. 06 ~ 03. 15 | Overhauled CWP at Hadong Thermal Power Plant. | (Domestic products) |
2007. 02. 20 ~ 03. 30 | Overhauled BFP at Daegu Combined Cycle Power Plant No. 2. | SS Model |
2007. 02. 05 ~ 02. 25 | Localized BFP parts and overhauled BFP at Shinincheon Thermal Power Plant. | Repair(US made pump) |
2007. 01. 26 ~ 02. 04 | Overhauled BFP at Jordan Rehab Power Plant. | DSC Model |
2006. 11. 30 ~ 12. 20 | Overhauled COP at Samcheonpo Thermal Power Plant. | (Domestic products) |
2006. 10. 16 ~ 12. 18 | Renovated SLP at Boryung Thermal Power Plant. | 10 units (domestic products) |
2006. 09. 15 ~ 09. 23 | Overhauled CWP at Hadong Thermal Power Plant. | (Domestic products) |